What happens if a mix's temperature differs from the established temp by more than 25°F?

It can still be used without issue

It should be rejected

When the temperature of an asphalt mix deviates from the established specification by more than 25°F, it is subject to rejection. This is pertinent because the performance of the asphalt mix is closely tied to its temperature during application. Variations outside of the specified temperature range can lead to inadequate bonding, improper compaction, and compromised durability of the pavement. A mix that is too hot may lead to excessive oxidation of the binder, while a mix that is too cold may not compact properly, resulting in weak pavement structure. Therefore, maintaining proper temperature is crucial for the integrity of the asphalt paving process, and any significant deviation necessitates rejection to ensure quality and performance standards are upheld.

Get further explanation with Examzify DeepDiveBeta

It is acceptable with a temperature adjustment

It needs further testing

Next Question
Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy